SJS Sheeting Limited was contracted to supply and install the roofing and wall cladding for a new unit in Bolton.
The roof has a total area of 1626 m2, a raked verge, an insulated membrane-lined valley gutter, and a mono-pitch roof area. We supplied TATA Trisomet 333 composite panels with Brett Martin Factory Assembled rooflights.
The roof was loaded and fully fixed in 5 working days. The wall cladding comprised a total area of 1016 m 2 and was a mixture of TATA Trisomet 333 and TATA Trimapanel in contrasting colour palettes, along with accessories installed. SJS Sheeting Limited managed the edge protection, safety netting, contract lifts, GRP to the raked verge and restricted access issues whilst completing the supply and installation safely, within budget and on time.
Total time on site: 7 weeks from start of roofing to completion of wall.
What
Materials Did We Use?
This project had many access issues to overcome, and SJS Sheeting were proactive in planning the most cost effective and productive method of installation, whilst ensuring the safety of the operatives.
Roofing Material
Tata Trisomet 333, 100mm core depth, outer skin; Colour Black RAL 00E53. Leathergrain finish. Inner skin; Bright White Lining Enamel.
Roofing Area
1626 m^2 loaded and installed in 5 working days.
Wall Material
1016 m^2 after the completion of the roof installation, SJS sheeting temporarily came of site to allow access for other trades, due to space restrictions. Returning on site, shortly after, to commence the installation of the wall panels.